In an effort to keep New Yorkers informed of the status of work at the Fulton St. complex, Transit sent out a month-at-a-glance poster earlier this week. I’ve printed the poster below. The work, according to Transit, will impact the IND platform at Broadway/Nassau this month. The work includes reinforcing the girders over the platform and digging pits on the platform so that crews can partially construct elevator shafts throughout all levels of the station. One day, a transit hub will arise.

After the poster come this week’s service advisories.

Below are the weekend’s service advisories. As always, these comes to me via Transit and are subject to change without notice. Listen to all on-board announcements and pay attention to signs in your local station. These are available in map form from Subway Weekender.


From 11:30 p.m. Friday, April 2 to 5 a.m. Monday, April 5, there are no 1 trains between 14th Street and South Ferry. The 2/3 trains provide alternate service, running local between 14th Street and Chambers Street. Free shuttle buses replace 1 trains between Chambers Street and South Ferry. Please note that during the day 1 trains skip 18th, 23rd, and 28th Streets in both directions. During the overnight hours, 1 trains skip 18th, 23rd, and 28th Streets only in the uptown direction. These service changes are due to Port Authority work at the World Trade Center site and concrete pours at 50th Street and 79th Streets.


From 11 p.m. Friday, April 2 to 5 a.m. Monday, April 5, 23 trains run local from 96th Street to Chambers Street due to concrete pours at 50th Street and 79th Street. Note: Overnight, 3 trains run local between 96th Street and 34th Street.


From 11 p.m. Friday, April 2 to 6 a.m. Saturday, April 3, and from 11 p.m. Sunday, April 4 to 5 a.m. Monday, April 5, Manhattan-bound 4 trains run express from Burnside Avenue to 125th Street due to a track chip out near 149th Street.


From 6:30 a.m. to 12 noon, Sunday, April 4, there are no 5 trains between 149th Street-Grand Concourse and East 180th Street due to track engineering near Jackson Avenue. Customers should take the 2 instead.


From 12:01 a.m. Saturday, April 3 to 5 a.m. Monday, April 5, downtown A trains run local from 59th Street-Columbus Circle to Canal Street due to a track chip out at West 4th Street.


From 12:01 a.m. Saturday, April 3 to 5 a.m. Monday, April 5, A/C trains skip Broadway-Nassau St. in both directions due to construction work at the Fulton Street Transit Center.


From 10:30 p.m. Friday, April 2 to 5 a.m. Monday, April 5, free shuttle buses replace A trains between Far Rockaway and Beach 90th Street due to track panel work.


From 12:01 a.m. Saturday, April 3 to 5 a.m. Monday, April 5, Bronx-bound D trains run on the N line from Stillwell Avenue to 36th Street due to switch renewal north of 9th Avenue.


From 12:01 a.m. Saturday, April 3 to 5 a.m. Monday, April 5, E trains are rerouted to the F line between Roosevelt Avenue and West 4th Street due to work on the 5th Avenue interlocking signal system. Customers should take the 6FR or shuttle bus instead. Note: Free shuttle buses connect the Court Square G/23rd Street-Ely Avenue E, Queens Plaza E, and 21st Street-Queensbridge F stations.


From 8:30 p.m. Friday, April 2 to 5 a.m. Monday, April 5, there is no G train service between Forest Hills-71st Avenue and Court Square due to fan plant work near Queens Plaza. During the day, customers should take the R. During the overnight hours, customers should take the E, making local stops between Forest Hills-71st Avenue and 36th Street. Note: Beginning 11:30 Friday, April 2, free shuttle buses connect the Court Square G/23rd Street-Ely Avenue E, Queens Plaza E, and 21st Street-Queensbridge F stations.


From 3:30 a.m. Saturday, April 3 to 10 p.m. Sunday, April 4, there is no J train service between Crescent Street and Jamaica Center due to track panel installation north of Woodhaven Boulevard. Free shuttle buses and the E train provide alternate service.


From 12:01 a.m. Saturday, April 3 to 5 a.m. Monday, April 5, Queens-bound N trains are rerouted to the R line from DeKalb Avenue to Canal Street due to track maintenance.


From 12:01 a.m. Saturday, April 3 to 5 a.m. Monday, April 5, Manhattan-bound Q trains are rerouted to the R line from DeKalb Avenue to Canal Street due to track maintenance.


From 12:01 a.m. Saturday, April 3 to 5 a.m. Monday, April 5, uptown Q trains run local from Canal Street to 57th Street-7th Avenue due to a concrete pour at Times Square.


From 10:30 p.m. Friday, April 2 to 5 a.m. Monday, April 5, A trains replace the Rockaway Park Shuttle S between Broad Channel and Rockaway Park due to track panel work.

You may also like

3 comments

Sunny April 2, 2010 - 8:44 pm

Couple of changes to the list:

The N and Q via R GO is cancelled.

There is an additional GO: Uptown 1 runs express from 96 to 145 Sts, 9AM to 1PM, Saturday

Reply
Scott E April 3, 2010 - 1:39 pm

When all is done, any word on whether the A/C station will still be called “Broadway-Nassau”, or will it be renamed to match the 2/3/4/5/J/Z (possibly M?) stations and the Transit Hub name?

Reply
Sue April 7, 2010 - 9:00 pm

The AC “Broadway-Nassau” name will change to “Fulton St” by the completion of the project.