Home Manhattan Getting closer on a Bleecker St. transfer

Getting closer on a Bleecker St. transfer

by Benjamin Kabak

Leo Villareal's Hive brings LED colors to the Bleecker St. station. (Photo by Matt Kroll/@TheRealKroll)

A few weeks ago, long-time SAS reader Matt Kroll sent me the photo above of Bleecker St. It’s a glimpse of the station’s newest art installation — a honeycomb of LED lights that change color above the new staircase. By Leo Villareal, “Hive” adds a touch of playfulness amidst the new transfer.

Of course, all of this may leave a curious New Yorker wondering how the MTA can go about installing a complex piece of modern art before completing a four-year renovation on a single subway station. To that end, I can provide no help, but it seems as though that elusive opening is moving closer to reality. Today, a reader informed me that the automatic announcements on the uptown 6 trains now announce a transfer to the B/D/F/M at Broadway-Lafayette, and another reader tells me that the station will open this month.

We’ve heard it all before, and so I asked Transit today for an official confirmation. They could not give me one. They have a date in mind, but it’s not yet ready for public announcement. So they’re getting closer and closer and closer and closer and…

You may also like

44 comments

Alex August 10, 2012 - 1:29 pm

Some of the improvements seem like an asymptote… closer and closer and close but never quite getting there.

Reply
Jerrold August 10, 2012 - 2:38 pm

That’s right, like .99999999999……….. or
1/2 + 1/4 + 1/8 + 1/16 + 1/32 ………

BUT, when they want to raise the fare, they go by a much more elementary mathematics.

Reply
Bolwerk August 10, 2012 - 5:42 pm

Actually, .9999… = 1. So does that summation.

Reply
Ben August 11, 2012 - 12:52 am

Only after an infinite number of steps, though.

Reply
Larry Littlefield August 10, 2012 - 1:39 pm

Perhaps the MTA is afraid that as soon as they give a public date, the contractor will stop working and require at $30 million change order to accelerate work to meet the date announced.

Bastards.

Reply
stairbob August 10, 2012 - 1:43 pm

My guess is that the art installer team is separate from the people who do the “real” work, and they do their thing as soon as the area they are installing to is ready.

Reply
SEAN August 10, 2012 - 1:55 pm

Magic 8 ball, will the transfer between the uptown 6 & the B, D F & M open soon? “the prospects no longer look Bleeck.”

Reply
aestrivex August 10, 2012 - 2:07 pm

It baffles me how the MTA prioritizes making things look pretty at a station that has recently been redone when their construction work is unfinished, their trains break down, and lots of other stations look like they haven’t been touched since 1978. Probably I am vastly overestimating the cost of the art relative to the operating budget for the other components, but instead of making the MTA look good, the overprioritization of the art makes me see them as looking bad and wasting their time and energy.

Reply
Shabazz August 10, 2012 - 2:39 pm

Its really lose lose for the MTA on this.

They renovate a station, people say.. wow it cost how much $$$ for this??? It looks ugly. It looks terrible.

They renovate stations and people say, omg! you spent too much money on the art!!

Also, I think the art is a small part of the renovation budget. Just saying.

Reply
Benjamin Kabak August 10, 2012 - 3:13 pm

Arts for Transit is such a miniscule part of the budget and so well regarded that it’s not going anywhere.

Reply
bgriff August 10, 2012 - 3:35 pm

Isn’t the MTA required by law to spend 1% (or some similar amount) of major renovation projects on art? Could still be argued it’s a silly policy, but at least it’s the state legislature’s policy, not the MTA’s.

Reply
petey August 10, 2012 - 11:52 pm

arts for transit is an excellent, excellent idea. i salute the person who inserted that clause.

Reply
aestrivex August 11, 2012 - 1:44 am

Yes, I know in my rational mind that it is really a tiny portion of the overall MTA operating budget. It is more that it just feels wrong to have this construction project be so late, with costs seeming to balloon out of control, yet also take the resources to put in this fancy artwork. To me, it just sort of feels like something is wrong no matter how negligible the costs are.

Reply
Peter August 10, 2012 - 3:46 pm

We can only hope that the new portions of the Broadway/Bleecker complex will be glistening and lovely, but in the course of these renovations there has been serious damage done to the B/D/F/M platforms — big swaths of tiling were ripped up in the course of stairway and elevator installation/repair and it’s been finished off in an alarmingly unprofessional manner: the replacement tiles don’t match the originals, there are bumps and bulges and the seams look awful.

I kept thinking that the current state was temporary and the platforms would be completely refinished before this was all done, but if an opening is imminent I guess that’s not the case.

I also notice there’s a lot of new water damage on the walls on these platforms — can’t say for sure it’s related to the renovations, but that seems likely.

Reply
mike d. August 10, 2012 - 5:22 pm

That area has a lot of water main breaks. B/D/F/M station needs a bath.

Reply
Alex C August 10, 2012 - 8:46 pm

The B/D/F/M station needs a complete makeover. The platforms, tiles and track look like they’ve been beat up for 30 years despite being relatively new. Amazing “Rehab” job.

Reply
Tower18 August 10, 2012 - 7:36 pm

I noticed something similar at Jay St when they were renovating that. Thing is, within 6 months, if not much less, everything reverts to the same stained shade and you can’t tell the difference.

Reply
Alex C August 10, 2012 - 8:47 pm

Jay St, two minor leaks aside, is still in excellent condition. Comparing it to the IND portion of the Bleecker/Broadway/Lafayette is not really fair. Jay still looks new, while the other looks awful.

Reply
mike d. August 11, 2012 - 4:14 pm

Just dont look up to the ceiling at Jay St. YUCK

Reply
John-2 August 10, 2012 - 5:09 pm

If the uptown 6 trains are announcing the transfer, it’s got to be pretty close to opening time (though I suppose checking the R-160 announcements on the F and the M to see if those have also be changed to announce the transfer to just the 6 train, instead of to the “Downtown 6” would be a way to corroborate that someone at Westchester yard didn’t simply jump the gun on the update).

Reply
PeterC August 11, 2012 - 12:11 am

If you walk by, you can see that the main thing they’ve been working on for the last few weeks is the elevators. For whatever reason, that seems to be the holdup.

Reply
Eric August 11, 2012 - 1:42 pm

Elevator always seem to be the holdup. The Court Sq transfer opened late because of elevator issues.

Reply
Jerrold August 11, 2012 - 7:55 pm

Like they can’t open an escalator while they continue to workon the elevators! Typical bureaucratic bullshit. How about all the stations that have ONLY stairs? Should they close down all of THOSE stations because they lack elevators? And that is not to mention the fact that many people are afraid anyway to go into a subway elevator.

Reply
Eric August 12, 2012 - 3:51 am

ADA…

Reply
Billy G August 12, 2012 - 6:45 pm

It wasn’t ADA before, and it isn’t officially open yet.

There’s no reason to block the stairs for ADA concerns alone.

John-2 August 12, 2012 - 9:19 pm

In a rational bureaucracy that’s what you’d do. But any new station access point built with federal funds has to by ADA-compliant from the micro-second it opens to the public, because it has to comply with the 1989 Americans With Disabilities Act unless you jump through hoops to get a waive, as the MTA did with Dyckman Street on the 1.

A federal waiver at Houston and Lafayette streets was never going to fly, even on a temporary basis. No working elevators. No compliance. No opening.

Billy G August 13, 2012 - 1:27 pm

That’s where the lawyers come in.

What’s the language? Is that open to foot traffic or officially open (e.g. ribbon cutting)?

If the former, then well that’s the cost of accepting the funding and the MTA should put that reason on notices across the entrance. No waiver?

Nathanael August 24, 2012 - 1:18 am

To tell the truth, the construction teams working on the elevators are probably blocking the access points to the stairs and escalators. The ADA encourages elevators and stairs to follow roughly the same paths so that people with mobility impairments can figure out which way to go.

A subway’s a crowded place to work and it will go faster if the construction team is allowed to occupy the stairs while working on the elevators.

Nathanael August 24, 2012 - 1:19 am

Also, it’s easier to get a temporary waiver if you have a past record of good behavior. The MTA has a record of BAD behavior when it comes to ADA compliance, so…

Bolwerk August 13, 2012 - 8:53 am

Kind of going off-topic here, but WTF is with those elevators anyway? I have been semi-frequently using the one at Court Sq. to carry things, incidentally, and it is absurd how slow it is. (My one or two recollections of other elevators from around the system is that they were similarly slow. Another example of the MTA not giving a shit about people’s time?)

Reply
Nathanael August 24, 2012 - 1:19 am

I do not know why the MTA cannot find suitable escalators. I am sure they are manufactured somewhere….

Reply
Nathanael August 24, 2012 - 1:19 am

rrrgh, “suitable elevators”

steve August 12, 2012 - 9:02 am

Leo Villareal’s Hive brings LED colors to the Bleecker St. station?
The sanitary conditions of the subway stops out of the area above 72 Street are appalling. The Broadway tunnel which connects the 191 Street Number 1 stop with Broadway has not been swept in months. There is standing water on the North side of the tunnel that runs its entire length (this is West Nile Virus Season). Half the lights do not work or are dimmed. It is unsafe, unhealthy, dirty, scary and dangerous.

This smacks of Nero playing the fiddle while Rome burns.

Reply
Billy G August 12, 2012 - 6:46 pm

Operating budget != CapEx budget.

Reply
Andrew August 13, 2012 - 7:37 am

That tunnel is NYCDOT property. It’s not under MTA jurisdiction. If you don’t like its condition, put pressure on DOT to do something about it. How the MTA is spending its capital dollars is irrelevant.

You do realize, I hope, that that 191st itself was fully rehabbed in 2003 (and that plenty of stations north of 72nd, and outside Manhattan, have also been rehabbed)? And that most of the beneficiaries of the new Bleecker transfer are not Manhattan residents?

Reply
Bolwerk August 13, 2012 - 9:00 am

I seem to remember federal funding guidelines either encourage or require some of the financing go to art. I would guess either the MTA was required to have some art, or they figured they may as well take the money if they’re going to get federal financing anyway.

Since that art is actually functional, if gaudy, maybe they actually found a good way to dispose of an otherwise pointless requirement.

Reply
HOLD August 23, 2012 - 3:25 pm

Yes this is true but on 1 artist? Why not spread that money out over 100-200 artists? Then they would actually have a collection that might be worth something one day and also be of education/cultural value to the NY community.

Reply
Nathanael August 24, 2012 - 1:22 am

1 artist per location; hard to do otherwise.

Reply
Davide-NYC August 12, 2012 - 12:48 pm

I have been waiting for this transfer to be possible for almost 40 years. This should be satisfying… when it finally opens.

Reply
A never-ending wishlist for transit improvements :: Second Ave. Sagas August 13, 2012 - 12:14 am

[…] daily ebb and flow of subway commuters. The louder complaints though concern the infrastructure. As pulsating LED lights have debuted at Bleecker St., riders from outside the core of the system are less than thrilled […]

Reply
Juan Castillo August 13, 2012 - 2:08 am

At what time will the new (B)(D)(F)(M)(6) transfer be open today?

Reply
Andrew August 13, 2012 - 7:37 am

Um, never.

Reply
HOLD August 23, 2012 - 3:13 pm

Villareal charges a min of around $100,000 for public projects of this scale. That’s just for his fee. The piece itself was between $200,000-$300,000 based on his previous sales. So the MTA spent between $300,000-$400,000 on ONE artwork in ONE station. If you remember last winter the Uniqlo ads all over the subway that added a much needed bump in the MTA advertising revenue. They were annoying by made the MTA enough money to save them from laying off 300 MTA employees. That means they made something in the 10-20 million range from Uniqlo ads.

Reply
Nathanael August 24, 2012 - 1:23 am

At least it was functional artwork. The MTA was able to eliminate the cost of installing ordinary lights in this area, I would expect… and LEDs are cheap to operate.

There have been worse choices for “Arts in Transit”. Other good choices include getting artists to do the wall tiling.

Reply

Leave a Comment