Category: MTA Construction

  • The people ride in a box suspended above the ground

    The Times diagrams a subway tunnel suspended in midair. Click to enlarge.

    About two weeks ago, The Times checked in on the Ground Zero construction and the rebuilding of the IRT subway tunnel that skirts the former World Trade Center site. While at the time, I didn’t have a chance to write about it, the article, still timely, warrants a look. It’s a fun little piece of engineering reporting about a unique stretch of the subway tunnel.

    David Dunlap’s piece focuses around the engineering challenges facing work crews as they work in, around and even under the IRT tunnel. Dunlap tells us about the work:

    The people don’t always ride in a hole in the ground. Those aboard the No. 1 train in Lower Manhattan are now riding part of the way through the air.

    There is no view to admire. The trains are still well below street level, on tracks running within a box-shaped concrete tunnel that bisects the World Trade Center site. But instead of soil, the south half of that 975-foot stretch of subway rests on a newly built network of brawny steel beams atop a forest of minipiles reaching down to bedrock.

    And in recent weeks, workers have dug out so much soil from around those minipiles that they have created an underpass beneath the subway large enough for construction machinery to pass through. In the reconstruction of the trade center, it is a significant milestone of east meeting west.

    Eventually, as Dunlap tells us, the entire subway box for the 1 train will be resting on minipiles and will last as such while the construction crews fill in the gaps around it with various parts of a subterranean structure.

    Now, I’m no engineer, but I love reading stories like this. There are so many unique aspects to the subways and the veritable city that exists under ground. Millions of riders on the 1 won’t ever know or notice that their trains are traveling over the ground while under the ground, but for those that do, it’s just another quirk in the New York City subways. And that, despite all of their problems, is what makes the subway so great.

  • Renovating the Rockaways

    Take the A Train past Howard Beach to the Rockaways. Journeying over the vast expanse of Jamaica Bay, the A train arrives in the Rockaways where the subway stations there are in a serious state of disrepair. If all goes according to plan, however, the MTA will begin work on a $190-million renovation project this fall that would see all nine of the peninsula stations receiving much-needed overhauls. The state legislature must approve the plans, and only after that can the Rockaways finally get modern stations with canopies and public address systems. [The Daily News]

  • Inside the circumferential subway route plans

    During his State of the MTA speech on Monday, Elliot Sander, MTA CEO and executive director, gave a nod to an idea whose time has come. “We need to take a close look at the Regional Plan Association’s circumferential subway line, which would convert the lightly used Bay Ridge freight line into a subway service that would run in an arc from southern Brooklyn to Queens to the Bronx,” he said.

    As the population in the City’s outer boroughs continues to explode, the Manhattan-centric limitations of the New York City Subway system are exposed for all to see. Work at LaGuardia but live in the Bronx? The commute involves packed buses or a subway trip into Manhattan and a bus to the airport. Live in Flatbush with family in the Bronx? Take a 75-minute, three-borough subway ride just to get there.

    Of course, most of these travelers eschew the subway for the relative convenience of an automobile ride. With the City’s preparing to crack down on auto use, circumstances are ripe for a circumferential subway route to connect Brooklyn, Queens and the Bronx while leaving Manhattan to its wiles. For those in the know, this plan — referred to as the Triboro RX — is not new. In fact, the Regional Plan Association has been discussing it since its Third Regional Plan published in 1996.

    Last summer, Michael Frumin fleshed out the idea and his work — available in this detailed Frumination post — shows how the city could usher in this rail line by using pre-existing rail rights of way and freight lines that don’t see much traffic. The route would swing through heavily underserved section of the city and connect with up to 20 other subway lines. As Frumin models it, at least 76,000 riders a day would use this line with nearly 45 percent of that total coming from people who do not currently use the subway. In other words, in this conservative model, this circumferential line could get a lot of cars off the road.

    While the nitty gritty — the Bay Ridge freight line, existing rights of way through Brooklyn, Queens and the Bronx — are important (and viewable here in picture form), the fun stuff is of course a map detailing the potential station stops and reach of what Frumin and the RPA have termed the X train. The train would start in Bay Ridge tracking west with the N line to 62nd St. Next, the line would head WNW, providing connections with the F, Q, 2 and 5 before making stops in Marine Park and Mill Basin East Flatbush and Brownsville, two areas sorely in need of a subway.

    In Canarsie, the X would meet up with the L to Broadway Junction. The train would then track the M to Metropolitan Ave. and head north through the underserved areas between Metropolitan Ave. and Jackson Heights in Queens. Heading northeast, the train would run through Astoria, across Randall’s Island and into the Bronx where it would cross the 6 and terminate with the 4, D and B at Yankee Stadium.

    For more of the technical challenges this route poses, you can check out Frumin’s overview and the alignment details. But engineering demands aside, this line could be a reality with less of a headache than anyone in New York would believe.

    Sure, there are challenges, and the MTA’s track record on recent construction projects is fairly terrible right now. But this line, more than the 7 extension, more than the Fulton Hub, more than just about any other capital construction project, would do wonders for the reach of the New York City Subway system.

    Right now, it’s a dream, but with a little initiative, this project could easily become a reality and a much-needed one at that.

  • NY Post: Show us the progress

    In a rather scathing editor, the New York Post rails on Elliot Sander’s State of the MTA address today. Citing the Fulton St. Hub, the delay in the Second Ave. subway and the whole flap over the 7 line extension, they note the MTA’s recent string of broken promises and wonder if it makes sense to look 40 years into the future if the MTA can’t even deliver one Lower Manhattan station on time and close to budget.”MTA brass will have to prioritize – and, more important, do a better job of managing projects and estimating costs,” the editorial says. “If the agency hopes to spend such vast sums, it first ought to show that it can deliver something for the money.”

    Admittedly, the Post makes some good points. As I’ve noted numerous times, the MTA cannot seem to finish projects on time or at budget. But right now, the City needs big dreamers, and Sander offered up a Big Dream on Monday. While the MTA should shoulder the blame for faulty projections and endless construction, our government should be investing more in the City’s infrastructure. When the future depends on it, there’s certainly enough blame to go around.

  • Inside the MTA’s $29.5 billion program

    The MTA, on Wednesday, unveiled a $29.554 billion capital plan designed to cover maintenance, upkeep and system-wide expansions from 2009-2014. The plan, as I noted yesterday, is substantially similar to the broad one the MTA presented to the public in November and would allow for a wide transit expansion in and around the New York Metropolitan.

    While presenting the package yesterday, MTA CEO and Executive Director Lee Sander called attention to the need for the congestion fee. “This proposed Capital Program will ensure that our transportation network is both maintained and expanded to support the region’s economic growth,” Sander said. “A fully-funded Program is critical to encourage transit use, to improve our customers’ experience and to keep pace with global competitors like London and Shanghai, where billions are being invested in transit each year. We won’t be able to get there without a robust funding package that includes congestion pricing.”

    In broad strokes, the MTA is planning a three-tiered approach to system improvements. The first tier involves “state of good repair, normal replacement and system improvement” including station renovations and the purchase of new rolling stock. The second tier focuses around the completion of current projections such as Phase 1 of the Second Ave. Subway, the pesky Fulton St. transportation hub and the East Side Access project. The final tier revolves around system expansion and includes communications-based train control system, Phase 2 of the Second Ave. Subway and the Metro-North Penn Station access plan.

    The capital plan also allows for system upgrades that would be enacted if the congestion fee is approved. These include more bus routes and buses; more service on the 1, E and F trains; and longer C trains. This is, of course, the most expendable part of the capital plan.

    For those of you with a taste for government documents, the entire 237-page plan is available as a PDF on the MTA’s Website. I’m going to take a look at what I consider to be some of the more interesting and tangible benefits.

    New Cars

    As part of its ongoing effort to maintain and upgrade its rolling stock, the MTA plans to invest nearly $1.5 billion in new cars over the next five years. The agency hopes to replace 500 cars and add 90 new ones to the system, all in the B division. Most interesting to rail fans is the announcement of the R179s. The MTA plans to purchase 208 R179s to replace the R44s currently in service as A trains. Discussion of the R179s has generated a six-page rumor thread on the NYC Transit Forums.

    Station Rehabilitation Plans

    Outside of the rolling stock, station rehabilitation plans are the most visible aspect of any capital program. The flagship plan is probably the Bleecker St./Broadway & Lafayette renovation. The MTA will finally connect the uptown IRT stop to the rest of the complex. The agency also plans to make the Grand Central stop on the IRT a little more rider-friendly with more staircases and better access points. The moving platforms at Union Square are in line for replacement as well.

    Additionally, the MTA is planning on overhauling 44 stations. Most of them — 41 — are above-ground stops in the outer boroughs. Nine stations along the Sea Beach line, 10 along the West End line, six in Far Rockaway, six in Rockaway, three along the Myrtle line and seven along the New Lots line are set for renovations. The MTA also plans to work on the 205th St. and 182-183rd Sts. stations in the Bronx and the IRT’s 14th St. stop in Manhattan.

    Technology Upgrades

    The MTA plans to bring communications-based train control to the Flushing and Queens Boulevard line. This represents the first expansion of the technological upgrades currently in testing along the L line. These upgrades should allow the MTA to increase service along high-demand train lines in Queens.

    Second Ave. Subway

    In the plan, the MTA admits that the budget for Phase 1 of the Second Ave. subway will exceed the initial, four-year-old estimates by a substantial amount. The new budget is set at $4.437 billion. The target completion date is also being pushed back to 2015 due to market forces and a weak economy. At the same time, the MTA is already planning for Phase 2, a good sign for those of us who don’t really expect to see a subway line heading up Second Ave. ever.

    What’s Missing

    In this ambitious, expensive and necessary plan, the aspect that jumps out at me is the utter lack of discussion about the future of the MetroCard. The document notes that “the current MetroCard system is still performing well.” However, with newer and better technologies available, I’d like to see the MTA consider a change to something more flexible than the MetroCard. Smart-card technologies really do speed up passengers at the point of entry.

  • MTA set to unveil $28-billion capital construction plan

    Back in November, during the MTA’s public engagement workshop in anticipation of the fare hike, Linda Kleinbaum, the MTA deputy executive director for administration, and Ernest Tollerson, the MTA director of policy and media relations, spoke at length about the MTA’s capital future. Today, the MTA will publicly unveil a final version of the plan Tollerson and Kleinbaum detailed to us a few months ago. The price tag is, in a word, shocking.

    The five-year plan, covering 2009-2014 and incorporating routine upkeep and maintenance as well as big ticket items, could cost as much as $28 billion, according to a report by the Daily News’ Pete Donohue. This new total represents an increase of around $6 billion since the MTA issued its preliminary capital plan at the workshop in November. I’m sure the cost will rise again.

    The plan encompasses a wide range of projects covering various MTA agencies. Included in it in November were financing plans for the completion of Phase 1 of the Second Ave. Subway and the start of Phase 2; a third track on the main LIRR line; Metro-North tracks on the Tappan Zee Bridge; Penn Station access for Metro-North; a Stewart Airport rail connection and the long-delayed computer-based train management system. My thoughts on this suburban-centric plan remain as I expressed them in November; I would rather see more of an investment in City-based transit expansion.

    But what’s done is done, and now the MTA faces an uphill battle to cobble up $28 billion over five years. Donohue has more on this ambitious effort:

    Details of the five-year construction and maintenance plan were still shifting, but the sources said the final price tag would fall in the $28 billion range.

    Some transportation officials, speaking on the condition of anonymity, expressed serious skepticism the Metropolitan Transportation Authority could secure enough city, state and federal funding for such an ambitious program.

    But two groups launched a major media campaign Monday to persuade state and city legislators to approve congestion pricing, which supporters say would quickly result in a federal grant of $354 million and generate $500 million annually.

    The timing of this announcement probably couldn’t be worse. The MTA, set to raise fares in less than five days, is forging ahead with an expensive plan that needs funding about is badly as it needs implementation, which is to say very badly. But over the last month, we’ve heard rumblings that the MTA may pare down and delay some projects while others are facing a host of financial issues.

    Meanwhile, as a few commenters have noted on Second Ave. Sagas, a lot of the budget projections for the Second Ave. Subway haven’t been updated in three or four years. Final price tags are bound to be higher than reported simply because construction costs have skyrocketed while our nation’s economy has tanked.

    In this atmosphere, the MTA is unveiling a capital campaign that will require massive investments by the state, city and federal government as well as the anticipated congestion pricing revenues, as Donohue explains. The region needs this capital plan; the MTA needs a lot of money. Where this will all lead is anyone’s guess.

  • On the precipice of a construction funding problem

    December’s groundbreaking ceremony for the 7 Extension may have been a bit premature. (AP Photos)

    Ah, remember those glorious days in December when hope sprang eternal and the City and MTA broke ground on the 7 Line Extension?

    Let the nostalgia wash over you because here comes the bad news: That 7 Line Extension project — and the Hudson Yards — development is in financial jeopardy. Surprise!

    In a lengthy piece on the future of Moynihan Station and the Far West Side, Daily News reporter Brian Kates drops in this five-paragraph bombshell:

    In his State of the City address last month, Mayor Bloomberg said the No. 7 extension was so crucial that the city “refused to wait for the MTA” and in December “broke ground on the first new mile of subway track the city has funded since the 1950s.”

    That’s the rhetoric. The reality is less optimistic.

    To begin with, the city puts the cost of the expansion at a deceptively low $2.1 billion – a figure it set in 2003 and hasn’t budged from despite skyrocketing construction costs. The MTA, which considers the proposed Second Ave. subway line a greater priority, has refused to pick up the tab.

    A $1.1 billion tunneling contract has been awarded, but to save an estimated $450 million, the city abandoned plans to put a station at 41st St. and 10th Ave.

    That means the line will run from Times Square to 34th St. and 11th Ave. without a stop – a decision that “puts at risk several million square feet of potential commercial and residential development” in the Hudson Yards, Sen. Chuck Schumer (D-N.Y.) said. “Development follows mass transit.”

    For a while, I’ve defended the MTA from a monetarily focused City. The City wants this 7 Line Extension; the City offered to pay for it; and then the City reneged on its promise. Considering the cost and the practical value of the extension, the MTA can spend its billions of dollars elsewhere for projects that would benefit more New Yorkers.

    But the news gets a little worse if we dig deeper. In a weekend Subchat post about planned renovations at the Shea Stadium 7 stop, a Subchatter noted that steel prices are at all-time highs. He says that New Yorkers should “expect cost over runs and cut backs on all [construction] projects.”

    So the cost of materials is skyrocketing, and the MTA and City are still using budget projections generated during our economy’s rosier days. Forget the 7 line; I want to know how this will impact the Second Ave. subway. The future cannot be bright for that project either.

    To bring this all back home, congestion pricing seems more important than ever to the MTA. While we can — and have been — debating the traffic-calming aspect of the congestion plans, the MTA will draw in much-needed revenue from a congestion pricing plan, and right now, they need the revenue. They need the revenue for operations; they need the revenue for capital projects. And as the tales of the 7 Line Extension show, transit is very closely related to the development of New York’s last frontiers. The future of the city — and the subways — is hanging in the balance.

  • MTA to delay and pare down, but not cancel, big-ticket projects

    The MTA will delay but not cancel big capital construction projects in an effort to address nearly $1 billion in cost overruns, Marlene Naanes writes in amNew York. While disappointing, this development comes as no surprise after the news this week has focused on runaway inflation and over-budget MTA projects.

    Despite these delays, however, MTA officials and transit advocates have stressed that the city will still enjoy the benefits; we just might have to wait a little while longer. And when it comes to the Second Ave. Subway, what’s one more year added to the 70 we’ve already been waiting? The MTA will decide in February just how they will delay or modify their capital construction plans to meet budget expectations. [amNew York]

  • Maybe granite and porcelain aren’t the best choices for a subway station floor

    It doesn’t make sense to lay the floor first. (Photo by Benjamin Kabak)

    As more details emerge about the MTA’s construction budget crisis, I keep coming back to Scott’s comment about the MTA and crown jewels. How do you balance form, function and visual appeal?

    Right now, the MTA is in trouble. As the Daily News noted yesterday, steel and concrete prices have “jumped 91% and 25% respectively” since the MTA budgeted for their projects. Considering how big a role steel plays in the subways, that jump has led to skyrocketing costs. But steel and concrete aren’t about making stations luxuriously opulent.

    Rather, granite and porcelain make stations overly expensive, and now, the MTA is saying that granite and porcelain have to go. Pete Donohue has more:

    Transit officials looking to save money may swap plans for fancy granite subway and train station floor tiles for a more economical – and drab – concrete. The potential savings are significant and the issue is generating strong opinions. “For me, this is a no-brainer,” said Metropolitan Transportation Authority board member Barry Feinstein, calling granite a “very expensive amenity.”

    According to NYC Transit, the MTA’s largest division, it costs $1.7 million to install granite flooring in the standard subway station, compared with $421,000 for regular concrete. After considerable expenditures, it is also scrapping a third type of tiling material: porcelain, which has been used exclusively in underground stations for the past eight years. Since then, 22 stations have received porcelain tile floors, at a typical cost of $1.4 million per station.

    Those porcelain surfaces have not held up well and are cracking and chipping, said NYC Transit spokesman Paul Fleuranges.

    Now, I’m with Feinstein. The only way to describe this option is as a no-brainer. But MTA board member Andrew Albert brought up another point. “A lot of people don’t believe a station renovation project is done unless the floor has tiles,” he said. “It doesn’t look finished.”

    And here’s where I think the MTA is messing up their construction plans. Why does the porcelain and granite look so bad? Why does it chip so easily? Because construction crews are installing the decorative aspects of the new stations well before they should be.

    Take a walk around the 59th St-Columbus Circle Station right now. It’s a mess. Construction walls are everywhere. Walls, ceilings, floors and staircases are all in various stages of completion. Dust floats through the station faster than pedestrian can maneuver. Yet, despite the mess, the new, fancy floors are already installed on the platforms, and they look terrible. They’re disgustingly dirty and slowly getting ruined. They’re also about six months old.

    Now, I have to ask: Does this make any sense? Usually in a construction project, the fancy, delicate parts go last because heavy machinery and constant work will ruin them. That’s exactly how the work at Columbus Circle has turned out.

    Clearly, the MTA needs to find a balance between building a functional transit system under budget and constructing something that looks nice. But the first place to start — besides in cutting down porcelain and granite use — should come in the planning stages. Put in the fancy stuff once it won’t get destroyed by ongoing construction.

  • And now it’s gone: the Fulton St. Transit Hub dome

    fultonstreetdomeless.jpg

    You get the point.

    Originallly, plans called for it to be 50 feet tall. Then, rising costs pushed the height down to 30 feet and then 20 feeet. Now, the glass dome that was supposed to sit atop the Fulton St. Transportation Hub is gone from the plans, the victim of inflation and rising construction costs, according to the MTA.

    Not only will these rising costs result in a drastically altered Fulton St. plan, but they could impact the other big-ticket MTA Capital Construction projects current in various stages of completion. According to MTA CEO and Executive Director Lee Sander, the MTA will soon begin a review of their skyrocketing capital budget in an effort to cut $1 billion from their four big projects — the Fulton St. hub, the LIRR East Side Access plan, the 7 line extension, and, yes, the Second Ave. Subway.

    William Neuman of The Times has more on what is sadly an unsurprising and familiar story for those of us waiting for the Second Ave. Subway:

    Soaring construction costs could force the Metropolitan Transportation Authority to scrap plans for an architecturally ambitious glass-domed subway station in Lower Manhattan and lead to more than $1 billion in cost overruns for the authority’s major expansion projects, officials said Monday.

    The rising costs could slow progress on the three so-called mega-projects needed to expand the capacity of the public transportation system, including a Long Island Rail Road link to Grand Central Terminal, a westward extension of the No. 7 subway line and the first leg of the Second Avenue subway.

    The news represents another setback for the subway station project, known as the Fulton Street Transit Center, which was envisioned as a central element in the recovery of Lower Manhattan after the terror attack of Sept. 11, 2001.

    “We’re just in the middle of a construction inflation crisis,” MTA Chairman Dale Hemmerdinger said. “And from our point of view as an agency that spends an awful lot of money, this is not good news.”

    While the future of the first phase of the Second Ave. Subway is ensured — the MTA, according to Sander, has the money from federal sources to finish the project — these budgetary problems may cause delays in all four major construction efforts, and the future of the Fulton St. hub’s outside appearance is very much in doubt. This fiscal crisis reached a head at the end of 2007 when the MTA put out a call for bids for the contract to build the ornate entrance to the hub including the dome. The contract, budgeted at $370 million, received one bid for $870 million. Back to the drawing board went the MTA.

    Now, the authority plans to chop that contract into smaller pieces. They anticipate finishing the underground work at Fulton St. by the end of 2009, but the completion date for what once was touted as Grand Central South is anyone’s guess. “I’m sad to say that we cannot build the transit center as currently envisioned in this market with the budget that we have,” Sander said.

    Yesterday, in the comments to my piece on the anticipated cuts to the Fulton St. dome, ScottE wondered if the MTA is overshooting on its plans. Does ever new project really have to be the crown jewel of the MTA, he wondered.

    Scott raises a very valid question, but in this case, I don’t think the MTA was aiming for the stars only to miss. The Fulton St. Hub, when completed, will be one of the most trafficked stations in the subway system, and it was, as Elizabeth H. Berger, head of the Alliance for Downtown New York, told The Times, supposed to be “center of our future.” But with a recession on our hands and constantly rising construction costs, the MTA is nearly back at square one. Now they just have to figure out how to design a new symbol for downtown while staying at or near budget. That is no easy task for an agency long beset with fiscal problems.