Home Second Avenue Subway Maloney grades the Second Ave. Subway

Maloney grades the Second Ave. Subway

by Benjamin Kabak

Earlier this week, I briefly touched upon a Second Ave. Subway report card released by Congresswoman Carolyn Maloney. At the time of my post, the report card had not yet been unveiled to the public, but late on Wednesday, Ben at The Launch Box secured a copy of the release.

What follows is Maloney’s assessment of this project. She gives the overall effort a B- but sees a modicum of light at the end of the proverbial tunnel. Take from this what you will. I’ll chime in with some commentary at the end.

Second Avenue Subway Report Card

On April 12, 2007, the Metropolitan Transportation Authority (MTA) celebrated the most recent groundbreaking for the Second Avenue Subway. At the time I expressed the wishful hope that the fourth groundbreaking on this project would be the charm. And it still may be, but there’s been a lot of sobering news since we celebrated the subway line’s most recent resurgence.

At groundbreaking, the plan was for the subway line to be completed in 2013, with three tracks at 72nd street and at a cost of $3.8 billion. Today, the MTA and the Federal Transit Adminstration (FTA) are discussing whether the subway will open in 2016 or 2018, projected costs are now estimated at $4.4 billion and we’ve lost the third track. Meanwhile, construction is having a dramatic impact on local businesses, residents and traffic. Roughly two and a half years into construction, it is time to take a look at the project and see how well the MTA is doing. Just as the City has found that report cards help evaluate the schools, this report card is intended to gain a better understanding of how the MTA is doing in moving forward with construction. This is a mid-term report, and the MTA has plenty of time to make up for early deficiencies.

WHAT’S BEEN WORKING

Project Merit: A+
All the reasons that led the FTA to consider this project one of the best in the nation remain strong factors. The subway will relieve overcrowding on the Lexington Avenue line, which continues to be the most overcrowded subway in the nation. When it is completed, it is expected to carry roughly 202,000 passengers a day, more than any other new start project in the nation. New Yorkers continue to rely on mass transit to commute to work, more than any other area of the country, and the Second Avenue Subway will provide much needed capacity on a system that has not grown in more than half a century.

Economic Benefits: A+
The Second Avenue Subway is creating 16,000 jobs, most of which are well-paid union jobs. At a time when the construction industry is slowing down, infrastructure construction like the Second Avenue Subway provides a vital source of income for thousands of construction workers. It has generated $842 million in wages and produced $2.87 billion in economic activity. Economists like Mark Zandi tell us that every dollar spent on public infrastructure increases GDP by an estimate $1.59. Using that formula, the Second Avenue Subway will generate nearly $7 billion in GDP.

Communication with the Public: B+
The MTA has held numerous public hearings during the environmental review portion of the project, and before property takings were approved. The MTA has also worked with Community Board 8, and other community boards, and has participated in Second Avenue Subway Task Force Meetings at least quarterly. As construction moves forward, they have agreed to attend meetings as frequently as monthly. In addition, the MTA has attended frequent meetings of the Second Avenue Business Association, and has worked with the City to mitigate impacts relating to sanitation, signage, traffic, utilities disruption and other matters. The MTA has hired Claudia Wilson who received plaudits at a recent Community Board 8 Second Avenue Subway Task Force Meeting for her availability and her willingness to solve individual problems. The MTA has also been willing to meet with local residents to resolve individual concerns relating to particular buildings. Nonetheless, despite these efforts, many community residents seem to know little about the project until construction begins in their neighborhood. Further, some details have not become public until it was considered too late to address the problem. For example, residents of buildings adjacent to ancillary facilities are being told that their windows will be covered by the new buildings. The likelihood was long known, but the MTA never told the neighbors until the designs were finalized.

WHAT NEEDS IMPROVEMENT

Planning: B-
The Second Avenue Subway is a complex project, and it requires a lot of coordination to bring all of the elements together. It is surprising, therefore, to find that there has been so little progress in two and a half years. Anyone with experience in New York City’s streets knows that there are few roadmaps for utility pipes, and that there are surprises. The MTA says it lost several months on the tunnel launch box because of where utilities were located. Delays of this type should have been expected and built into the schedule. Further, the MTA should have investigated the structural integrity of local buildings long before masonry started falling. If there had been better coordination between the MTA and city agencies, blasting would not have been delayed in order to allow adjacent building to be appropriately shored up. All of this should have been done much earlier in the process.

Construction Management: B-
The MTA is working on many large projects simultaneously and it needs to ensure that this project is getting the attention it deserves. The 7 train extension (which does not need federal approvals and is being constructed in a less dense area) began long after the Second Avenue Subway, and the tunnel boring machine is already in the ground. The MTA has recently taken steps to pull up its grade by getting permission of the MTA board to allocate federal funding so that contracts can be bid more quickly. It has broken contracts into smaller chunks to allow for more competitive bidding to bring costs down. It has created a schedule of contracts so that the public can follow its progress to make sure that contracts are being bid on time.

Mitigation of Construction Impact: C
The MTA seems to want to try to mitigate the impact of construction on local residents and businesses. They have been diligent in meeting with local businesses. They have hired people who genuinely appear to want to work with the community to address individual concerns, and some members of the community have complimented their efforts. They have reduced the number of buildings they have condemned to limit the number of people who will be losing their homes. They have created a Shop Second Avenue campaign to try to drive customers to affected businesses. Unfortunately, more than a dozen businesses have closed along the subway’s construction zone despite these efforts.

On Time Record: C
When this project went into Final Design, the MTA was projecting a completion date of 2012. By the time the project broke ground, they projected a completion date of 2014. This summer, the MTA began projecting a 2016 completion date. Some argue that the project will not be finished until 2018. Others suggest that the MTA could get its act together and move forward more aggressively, finishing earlier than December 2016. There’s a lot of room for improvement here.

Staying on Budget: C
When the full funding grant agreement was signed, this project was supposed to cost $3.8 billion. Today, the MTA is projecting $4.4 billion. It’s not going to be easy to find the extra funds, particularly when there are so many other competing projects. The longer this project takes, the more it will cost. The MTA is taking advantage of the dip in the economy to bring some of the costs down, and it has scrapped plans for a three track system to reduce costs further. But unless the MTA meets its projections, it will be very hard to find the resources to complete this project.

Progress Toward Completion: C-
Thus far the MTA has bid 3 of 11 contracts. It has completed some of the preparatory work for the tunnel launch box, including building the slurry wall, but no blasting has begun. Thus far there has been no tunnel dug, no shafts completed, no station entrances built, and no ancillary facilities built. It’s early in the project and preparatory work does need to be done before we should expect to see tangible results. Two and a half years into construction, we hoped for greater progress.

FINAL GRADE

Overall Grade: B-
The Second Avenue Subway is crucial to the economic future of New York. It needs to be built. The MTA has an ambitious construction schedule, and it needs to put its full attention to making sure that this project is moving forward with all deliberate speed. Up until now, the project has been marred by missed deadlines, cost overruns and a harsh impact on local businesses. There is a lot of room for improvement, but also the possibility that the project is now starting to gain momentum.

* * *

It’s tough to dispute Maloney’s assessment. She is brutally honest about the pace of progress, and in fact, her C grades for the project’s on-time and on-budget records could even be considered generous. In the end, the MTA should inform the public why this project is nearly six years behind schedule and what the agency is doing to address these concerns. The city needs the Second Ave. Subway, and after so much disruption on the ground, further delays should not be tolerated.

“The new subway line will be great for the East Side in the long run, but the construction process is clearly devastating the neighborhood,” Upper East Side Assembly representative Micah Kellner said of Maloney’s report. “It is simply unacceptable that the time line is endlessly revised with the excuse that the original end date was merely ‘optimistic’ and arbitrary. The MTA must be held accountable for the construction’s impact on the lives of residents and the livelihoods of business owners. This report only serves as a reminder of the serious work that needs to be done to streamline this project.”

You may also like

19 comments

Alon Levy October 1, 2009 - 3:32 am

SAS is budgeted at four times the per-kilometer cost of deep-level subway construction in Tokyo. Even an F for planning and budget is charitable.

Reply
Christopher October 1, 2009 - 8:57 am

Building rail in the U.S. is much higher than the rest of the world because we have (a) benefit cost for labor that aren’t factor in when you have socialized system of pension and health benefits and (b) have much looser laws about individual property rights. Both those factors make any type of large construction project in the U.S. a lot more unaffordable.

Regardless, I wish Maloney had spent more time on the loss of the 3rd track. That was a dumb move that will seriously impact the effectiveness of the overall operation of the line, (especially in it’s full length, and the cost of removing it on percentage basis was hardly a drop in the overall cost of the project. If it wasn’t built up front, it should have at least been accounted for and space included for it.

Reply
Marc Shepherd October 1, 2009 - 12:26 pm

The third track was not in the original design (it was added later), and many comparable junction points do not have anything similar. Remember, it was not a third track for any appreciable distance, but only at one station.

While it would have been marginally helpful and I was sorry to see it go, I do not consider it a serious loss. Most of the construction cost is tied to the cost of excavation, so “leaving space for it” would not really have been an option. Either you build it or you don’t.

Reply
Alon Levy October 1, 2009 - 2:04 pm

It’s not the US – it’s New York. In San Francisco and Los Angeles, subway construction is budgeted at about $250 million per route-km, compared with $1.7 billion per route-km for SAS.

Also: none of the subway lines in Tokyo (or any other city except Seoul) has multi-track sections, except lines that run both local and express trains and need some place for express trains to overtake locals.

Reply
Christopher October 1, 2009 - 9:02 am

Also, with respect to Tokyo. Tokyo has a much better understand of what lies beneath it’s roadways. The city is mapped within an inch of it’s life, most of it built within the contemporary era of the last 60 years, unlike our 19th century era city. And because of earthquakes there is even more centralized planning and understanding of it’s infrastructure. We can’t blame the MTA that it’s dealing with a 400 year old city, most of which was built in the gung-ho railroad days by private entities by underpaid foreign-born workers without detailed plans.

Reply
Kid Twist October 1, 2009 - 9:38 am

The 400-year-old city lies several miles downtown. The Upper East Side did not start to get built up until the 1880s, after the els arrived.

Reply
Jerrold October 1, 2009 - 6:35 pm

Good point, Kid Twist!
AND, coming to think of it, that means that 100 years ago that area HAD rail rapid transit. Now, it does not.

Many people think that the BIGGEST mistake in NYC history was the razing of the old Penn Station.
It WAS a big mistake, but an even BIGGER mistake was the razing of the 2nd Ave. and 3rd Ave. els without the immediate beginning of the construction of a subway to replace them.

Reply
Boris October 1, 2009 - 9:55 am

Isn’t construction speed a function of the availability of money? If there was more money and/or contract awards went faster, wouldn’t there be two stations being worked on simultaneously, two tunnel boring machines, etc?

Reply
Kai October 1, 2009 - 10:23 am

Also true… If there were enough money all four phases could be built at the same time!

Reply
Scott E October 1, 2009 - 10:37 am

That could be risky. If an underground obstacle were discovered and the TBM had to veer around it, the different segments might not meet up. Better to keep continuing in one direction. Also, if mistakes were made at the beginning, it’s better to fix them now and learn from it so they’re not made in subsequent phases, rather than to go back and repair all 8 miles.

Besides, do you really want to see eight full miles of Second Avenue disrupted at the same time? You see what happens when just a few blocks are under construction.

Reply
Alon Levy October 1, 2009 - 2:07 pm

In the early 1900s, they disrupted the full 9 miles of the first subway line at the same time with cut and cover construction.

It’s better to be quick about it than to try to prolong everything.

Reply
rhywun October 1, 2009 - 11:00 am

“a system that has not grown in more than half a century”

If by “not grown” she means “rapidly shrunk”.

Reply
Marc Shepherd October 1, 2009 - 12:22 pm

I think those grades were too kind.

Reply
Leave Room for Dessert - City Room Blog - NYTimes.com October 1, 2009 - 12:56 pm

[…] Second Aveune subway received less than stellar marks on a recent report card. [Second Avenue […]

Reply
Publius October 1, 2009 - 2:53 pm

Carolyn Maloney’s grade: D+

Reply
peter knox October 5, 2009 - 12:47 pm

I don’t know why I bother to respond to this nonsense, but I’ll wearily continue to try to inject some truth into this farce. To fixate stubbornly for 80 years on an idea that cannot be realized is not an example of an A+ project; in an individual it would be described as a mania. Cities and their representatives can clearly go nuts, also. To repeat ad nauseam, the subway is not being built. Not one inch of it has been built. And nothing will be built until they resolve this little problem of three buildings on teetering foundations. That will take year(s) to correct. Phase one is going to cost at least 6B and take at least another 10 years. By that point who knows how many times fares and taxes will have been raised to pay for it. And who knows how many lives will have been destroyed by its criminally-negligent construction.

Reply
In second annual report card, Maloney sees SAS improvements :: Second Ave. Sagas September 27, 2010 - 12:03 pm

[…] has gone, the Upper East Side’s politicians see only incremental improvement. After handing out a B- last year, Rep. Carolyn Maloney, Assemblyman Micah Kellner, and Councilwoman Jessica Lappin have given the […]

Reply
From Maloney, a B for the future T :: Second Ave. Sagas September 26, 2011 - 12:01 am

[…] opportunity to unveil her third annual report card for the project. After giving the subway project a B- in 2009, she graded it a B last year. This year, it gets another B. Said Maloney: “The MTA finished […]

Reply
What Rep. Maloney’s Second Ave. report card doesn’t say :: Second Ave. Sagas July 29, 2013 - 11:46 pm

[…] for it to open in late 2016 — if it indeed opens in late 2016. After giving the project a B- in 2009 and a B in 2010 and 2011, Maloney has now given the project a B+, its highest grade in four report […]

Reply

Leave a Comment