Home Second Avenue Subway An SAS date with the tunnel boring machine

An SAS date with the tunnel boring machine

by Benjamin Kabak

At the end of last week, I profiled the tunnel boring machine that the MTA said would soon be lowered into the launch box below Second Ave. Yesterday, we learned that the big date is sooner than we think.

The SAS TBM – whose 22-foot cutterhead is shown above – is heading for Second Ave. Over the next three weeks, according to a notice posted on the CB8 website, the TBM will be lowered into the launch box and reassembled. It will then start drilling out the Second Ave. Subway tunnels. The notice reads:

Tunnel Boring Machine delivery notice

Over the next three weeks, between April 12 – 30, 2010, we plan to deliver to the work site and start assembly of the 22-foot diameter Tunnel Boring Machine (TBM), all its associated back-up equipment, as well as the excavation material haulage system and removal equipment.

The TBM and associated back-up equipment are over 300 feet long, and consists of the TBM itself and eighteen double-deck rail cars on which the actual back-up equipment is carried. In addition, locomotives to haul material into the tunnel and rail cars for removal of excavated material will also be delivered. The total weight of the TBM itself is of the order of 485 tons, and will therefore be delivered in smaller pieces and assembled on site. Some of the individual heavier components of the TBM weigh between 60 to 125 tons. Similarly, the rail cars and back-up equipment will be delivered as individual components and installed/assembled in the Launch Box. All lowering of the TBM and back-up components will take place at the deck opening between 92nd and 91st Streets. A large crane will be located south of this deck opening to perform the lowering operations.

Due to the size of the machinery and DOT oversize load restrictions, the delivery of this equipment will need to occur at night between the hours of 11:00 pm and 6:00 am, on weekdays only. Lifting the equipment off the trucks and lowering into the launch Box will require up to three lanes of Second Avenue to be closed to traffic for two weeks (April 12 through April 23) and one lane for one week (April 26 through April 30) between the hours of 11:00 pm and 6:00 am. In addition, all lanes will be shut down during the actual pick of the equipment for safety reasons. Second Avenue will remain open to traffic during other times. Staging of the delivery trucks will be alongside the Launch Box and possibly at discrete locations north of 95th Street.

Please be advised that a safe work plan for this operation is in place. Due to the nature of this extended operation and safety precautions to be taken, the area will be lighted and some noise during its performance is unavoidable. MTACC will make every effort to minimize any impact to the community during these night-time hours.

As I mentioned on Friday, this TBM was made 30 years and was reconditioned to be “like new.” It has been put to use on four other projects, including the 63rd St. subway tunnel, and it was tested just a few weeks ago in Newark, NJ. Watch below a video of the testing, and for more on this TBM, check out coverage on The Launch Box and Upper Green Side.

Image above courtesy of MTA Capital Construction. Click it to enlarge.

You may also like

8 comments

Boris April 13, 2010 - 2:00 pm

Sounds like the perfect time for every East Sider to take a nice long vacation.

Reply
Jerrold April 13, 2010 - 6:06 pm

It’s VERY good news that the “real” tunneling for the SAS is about to finally begin. I only wish that definite plans were in place for Phases 2 through 4.

Reply
Woody April 14, 2010 - 3:50 pm

Yes, VERY good news. Surely nearing or past the point of no return. With the TBM in the ground, it would cost so much to stop the job that the politicians will have to let it keep going, even if the State is broke.

Reply
Justin Samuels April 14, 2010 - 10:35 am

Well, Phase 2 tunneling is mostly complete. They have to build the stations on that section, and extend the tunnel from 120th and 2nd to 125 and Lex, which won’t be too difficult. THey built the tunnel from Canal Street to Hanover Square (stations have to be built) so the phase requiring work from Scratch is really Phase 3.

Probably as the tunneling from the Second Avenue Subway on the UES is finished next year, the MTA will be able to hit the feds up for money for the other phases. The feds will be doing more to fund mass transit and other infastructure.

Reply
Alon Levy April 15, 2010 - 4:45 am

The stations cost a billion dollars apiece. Building a tunnel without stations is pretty cheap, unless the project is East Side Access.

Reply
Justin Samuels April 19, 2010 - 9:17 pm

For East Side Access, a new station still has to be built under Grand Central, and that’s still expensive. For Phase 2 of the Second Avenue subway, my point stands, the tunneling in Spanish Harlem was done in the 70s. They just need to build the stations, and while expensive, building even just a tunnel, with all the prep work that must be done, is still pretty costly.

Reply
Second Avenue Subway Hearing « Inquiry004's Blog April 19, 2010 - 5:58 pm

[…] caused numerous evictions of both residents and businesses due to installation of ventilation and underground digging. According to the MTA, it makes its best efforts to give those affected advanced notice based on […]

Reply
Cutterhead Support arrives at the SAS launch box :: Second Ave. Sagas April 21, 2010 - 7:14 pm

[…] Bridge at 8 p.m. and was lowered underground shortly before 11:30 p.m. According to my sources, the Cutterhead itself will be arriving tonight at around the same time, and although the weather isn’t the […]

Reply

Leave a Comment