
Few projects symbolize the frustration of major public works in New York City quite like the Fulton Street Transit Center. Planned as a post-9/11 revitalization project for Lower Manhattan, the Transit Center was originally supposed to be completed by 2007, but when federal funds dried up in the mid-2000s, the project languished. It will be finished in 2014 and at a cost of $1.4 billion, nearly twice as much as originally projected.
Yesterday, the MTA again reiterated that the project is on time and on budget. Things are actually happening at Fulton Street. The press release has the details:
The Fulton Street Transit Center is more than 50 percent complete and is on track for its scheduled overall June 2014 completion, with the MTA opening up various parts of the complex for public use before then. MTA Capital Construction continues to reach new milestones, most recently installing the first superstructure steel for the Transit Center Building on March 9, 2011.
A 100-foot tall tower crane has been installed on Broadway and steel erection will continue over the next several months, finishing by the end of 2011. One train car length away, restoration of the historic Corbin Building is continuing on both the interior and exterior façade, with the north wall of the building fully restored to allow for the adjacent Transit Center Building to commence steel work. Restoration of the Corbin Building, an 1888 landmark, is expected to be complete by the end of 2012.
The reconfiguration and rehabilitation of the Fulton Street A/C Station is one of the most complicated aspects of the entire complex and continues to progress well. All structural work has been completed on the A/C Mezzanine East and final finishes, including glass tiles and a LED wayfinding band, which are being installed on the corridor walls. Work also continues to progress on the new entrance at 135 William Street which is scheduled to open in July. An additional entrance at 150 Willam Street will be open by the end of 2011 and in 2012 a new elevator will be installed in the station at 129 Fulton Street.
I’m quite curious to see how the LED wayfinding band operates. At some point, it will be operational, and it could serve as a harbinger for technology to come. A few maze-like stations throughout New York could use similar features.
Ultimately, the current progress at Fulton Street is a testament to an MTA without unsettled leadership atop Capital Construction and a steady flow of funds for the project. With money and direction, construction projects in New York can actually move forward albeit at a rather slow pace.
Leave a Reply