
Unfortunately, for the MTA and its contractors working underneath the Upper East Side, time is marching inevitably forward toward December. As the agency is facing mounting pressure both internally and externally to deliver Phase 1 of the Second Ave. Subway by the end of the year, we are receiving monthly updates in the form of MTA Board meeting materials on the project, and each month the story is the same: The MTA’s work schedule is aggressive and not being met with the usual suspects looming as issues. Last month, I detailed how escalators and elevators may again delay the opening of a major MTA project, and this month, we hear more of the same.
The latest is found starting on page 48 of the MTA Capital Construction pdf that the MTA’s oversight committee will discuss later this morning. The short of it is that one station — 72nd Street — may gum up the works for the rest of Phase 1, and overall, escalator and elevator installation efforts are falling behind schedule. Right now, four of seven key milestones at 72nd Street are behind schedule. These involve elevator and HVAC installation and tunnel vent fans. At both 86thand 96th Streets, escalator and elevator installation is a few weeks behind schedule. All work at 63rd St. remains on schedule even as half the station continues to serve F trains.
In each case, the MTA claims the delayed timelines will not affect the projected December 2016 revenue service date, but the agency’s independent engineering consultant isn’t as confident. First, the IEC notes that only 70 percent of tracking milestones met in March were met and that the lack of improvements at 72nd St. mean that the problems with escalator and elevator installation “remain close to impacting the target [revenue service date].” As they have done so in past months, the IEC again warns that the MTA’s testing schedule is “highly compressed which maximizes the demand on NYCT staff.” But this is an all-hands-on-deck effort right as the MTA is engaged in what is essentially an eight-month sprint, but demand on staff is an ancillary concern at best.
Ultimately, the IEC is worried, and they sum up their concerns succinctly:
- The work effort at the 72nd Street Station site has not reached the level necessary to support the accelerated schedule.
- Late design changes have continued through March and the backlog of changes may present a risk to the scheduled completion of the testing program.
In response to this development that one of three stations could hold up the entire project, a few readers have asked me if the MTA could open Phase 1 but keep 72nd Street closed until elevator and escalator installation is completed. As of now, this isn’t a particularly likely scenario and may present a challenge to the way the MTA operates. For now, MTA Capital Construction, a distinct agency under the MTA umbrella, has control over the entirety of Phase 1 of the Second Ave. Subway, and when all systems are completed, tested and accepted, they’ll turn over the project to MTA New York City Transit, a different agency under the MTA umbrella. (For the 7 line extension, MTA CC didn’t turn over the reins until shortly before the ribbon-cutting on the station, and even now, remediation work is ongoing.)
MTA CC can’t turn over part of the project while retaining control over another part, and the MTA can’t get certified to open the station with, say, only escalators and no elevators due to ADA compliance issues. It is essentially an all or nothing proposition. So everyone is holding their collective breaths as December ticks closer. We’ll get another report in May, but the key updates will arrive in June when the testing schedule must come into focus to meet the December revenue service date. We won’t know until very late in the year if the project will be delayed, but the warning signs are there. Anyone betting on the actual opening date?
Leave a Reply