While speaking with the Long Island Association earlier this morning, MTA Chairman Joseph Lhota let slip the news on East Side Access that has been a few months’ coming. “We were originally looking at 2018, but the most recent analyses puts the opening at 2019,” Lhota said. “I don’t want to see it go past 2019.”
LIBN.com has more:
The problem with East Side Access isn’t digging below Grand Central Station, where “cavernous tunnels” have been carved out, but on the Queens side of the project. Tunneling underneath the Queens rail yard near Jamaica, where trains from Amtrak and Acela are stored in addition to MTA’s own vehicles, has become an issue.
Contaminated soil languishes and must be disposed of properly, and unlike closer to the water, the ground is soft rather than rocky. Lhota said workers have also run into springs and brooks that nobody knew existed below the surface. The MTA has brought in experts from Europe to help with developing a plan going forward.
To call this a nightmare scenario for the MTA would not be hyperbole. Initial estimates, clearly optimistic, placed the completion date during 2012, and the timeline slipped first to 2014 and then to 2016 and then to some undetermined date in the future. Now, it seems, we will have to wait seven more years for this project, with substantial tunneling completed, to see revenue service.
There is, as yet, no word what this timeline will mean for the costs. I’ll have more info as I receive it. At least for now those bemoaning Metro-North service into Penn Station will have a good decade to refine their arguments.
* * *
(Update 5:30 p.m.): Later in the day, the MTA put out the following statement as the authority acted to temper down fears of a never-ending project:
The Metropolitan Transportation Authority is reevaluating the risks in the construction schedule for the East Side Access project, and plans to present its findings to the Capital Program Oversight Committee later this month. One preliminary analysis of risk factors has indicated the completion date may move to 2019, as East Side Access construction intensifies in the busiest passenger rail yard and the largest passenger rail interchange in the nation.
The analysis is not complete, and the MTA is identifying ways to mitigate those risk factors to allow the project to be completed as early as possible. The MTA continues to work with its partners at the Federal Transit Administration to update the East Side Access funding agreement to reflect the new schedule.
Amtrak and the MTA are working closely together on East Side Access and improvements to the East River tunnels and the Harold Interlocking to accommodate the roughly 500,000 passengers who rely on 1,200 train movements through the region each day. Senior executives at Amtrak, the MTA and NJ Transit regularly meet to coordinate construction activities and do everything possible to keep work moving forward.
We’ll have a more definite timeline later this month when the MTA Board gathers to discuss this delay-plagued project.