As time marches on and the subways enjoy record-setting crowds (more on that later), various capital construction deadlines are fast approaching. As we know, two megaprojects — the 7 line extension and the Fulton St. Transit Center — are due to wrap this year, after nearly seven years of construction. Due to the delays plaguing the escalators and elevators at the deep 34th St. station along 11th Ave., the Fulton St. ribbon-cutting has leap-frogged the 7 line. According to MTA Board documents released yesterday, Fulton St. will open to public on Thursday, June 26, 2014. Save the date.
Meanwhile, mitigation work and acceptance testing continues on the Far West Side, and the MTA is still committed to delivering the 7 line in the fall, nearly 11 months later than scheduled. For now, the official word is still “November,” but according to an engineering report contained within the MTA’s materials this week, that date could hit December if problems aren’t resolved. The winter solstice is December 21. So the MTA has three weeks in December in which it is still technically fall to deliver the project. Hold your breath.
Finally, over on the East Side, the Second Ave. Subway continues to be on pace for a December 2016 revenue start date, but the documents detail some slippage. Construction crews have burned through approximately half of the project’s planned contingency days, and a few delivery dates have been pushed back. Still, until we hear otherwise, December 2016 it is. That’s only 33 months away, and the real estate market is responding in turn.