As Monday dawns, the MTA Board Committees will gear up for a full day’s worth of meetings. Despite the fact that the fare is set to rise in March, we won’t hear hand-wringing over the fare hike amounts or even new proposals as, by a few accounts, Gov. Andrew Cuomo is putting pressure on MTA leadership to delay public announcement of any fare hikes and toll increases until after Election Day. There’s nary a mention to be found of the looming rate increases in this month’s Board materials, and usually, the MTA announces the plan in mid-October.
What’s done is done — or better yet, what’s not done isn’t done — on that front, and for now, we’ll move on to other things such as what’s up with these never-opening capital projects? October will end this week, and the Fulton St. Transit Center, once expected to open in late June, will remain shrouded in construction. This week’s Board materials offer few clues to the project’s opening. A note in a presentation to the Transit Committee states only that “the Fulton Center Opening date is currently under review” while the opening date is projected to be some time in Q4. Work started, by the way, in December of 2004.
The presentation to the Capital Program Oversight Committee offers a little bit more information. The Transit Center building contract is expected to be completed before the end of December, and it seems that only a few items remain outstanding. But a few items are enough to delay the whole thing. As the materials say, “Substantial completion of this contract has been delayed due to extended testing and commissioning and subsequent punchlist items.”
Information regarding the 7 line is even harder to find this month. The MTA isn’t offering its Board any further information on the problematic elevators and escalators that have delayed the project, and although we’ve heard February 2015 as an opening date, the latest MTA docs give the agency some leeway. Currently, revenue service is projected to begin during the first quarter of 2015 — which runs through the end of March. The one-stop subway extension was once supposed to be open by the end of 2013, the first quarter of 2014, fall 2014 and then Q4 2014, but now it seems, one way or another, we’ll wait until late winter or even early spring.
All of which brings me to the Second Ave. Subway. Construction on the three-stop East Side extension of the Q train is continuing apace, and the MTA still believes they have approximately 26 months left on this project before revenue service begins. The Board materials confidently state a December 2016 ribbon-cutting, and although a few years ago, the feds disputed this projection, the MTA has vowed to open the subway on time. That said, the MTA has also vowed to open the Fulton St. Transit Center on time and the 7 line on time. Given the betting line, wouldn’t you take the “over” on December 2016? I know I would.
On a more immediate level, though, as the MTA wants political support for its $30 billion, five-year capital plan, the agency needs to show that they can deliver something somewhere on time or at least learning why they can’t. The aspect of the Fulton St. project that’s being delayed is a fancy headhouse while, seemingly, the complicated underground work has largely wrapped; the 7 line hasn’t opened because of vent fans, inclined elevators and long escalators — hardly technology unique to New York. We won’t know what happens with Second Ave. for another 18-24 months, but whatever remains of the MTA’s capital project credibility is riding on it.