Renderings for a $10 billion bus terminal that will take 15 years to build. (Via Port Authority)
While discussing on Thursday the Port Authority’s apparently gold-plated plans to build the world’s most expensive bus terminal in the heart of Midtown, the bi-state agency’s board let slip a joke. Concerned with the $10 billion price tag, one Port Authority Board member suggested a design competition similar to the one Gov. Andrew Cuomo has hosted for the beleaguered LaGuardia Airport. John Degnan, PA chair, seemed amenable to the idea so long, as he said, as “maybe not a Spanish architect” emerge the winner.
This was, of course, a not-so-veiled jab at Santiago Calatrava and the World Trade Center PATH Hub’s ever-escalating costs. For the Bus Terminal though, the Port Authority doesn’t even need a Calatrava to drive up the costs. Their own engineering consultants were more than happy to oblige. Despite the shocking costs, though, the Port Authority’s overseers all seemed to agree that inaction isn’t an option, but moving forward on a $10 billion replacement plan is a tall order. Who will foot the bill? How? And why does this thing cost so much anyway?
As part of the master planning effort to replace the aging bus terminal, the Port Authority released an updated report [pdf] from its engineering team. In broad strokes, something has to give. The Port Authority Bus Terminal is essentially at capacity, and ridership models predict a continuing upward trend over the next 25 years. Currently, as the report notes, “peak demand exceeds capacity,” and the problem will only get worse over the next few decades.
To top things off, the current bus terminal is structural deficient and must be replaced. The report makes it very clear: “The structural slabs supporting bus operations will need to be replaced in 15-25 years,” and doing so requires replacing the terminal entirely. Additionally, the PABT “was not built for taller, longer, heavier modern buses.” It simply can’t withstand the physical pressure today’s coaches place on the building.
So what’s the $10 billion solution? To build a bus terminal that can, in the words of the PA, handle the seating capacity of Citi Field every peak hour. The devil is in the details on the various plans. The most expensive involves a rebuild of the current terminal and all of its supporting infrastructure at their current locations along with additional capacity to meet 2040 ridership projections. (Whether 2040 is too soon a horizon for an infrastructure project that will take 15 years to complete is an open-ended question that bears investigation.) This plan requires an interim bus terminal and contains only one tower above the terminal.
The other proposals are a little cheaper with potentially more development options, but each contain their drawbacks. One doesn’t include intercity buses; a few plans move the terminal to 9th Ave. — a long block away from the nearest subway station; the cheapest couldn’t even handle today’s crowds and would require additional facilities elsewhere to meet demand. The costs and locations of those aren’t baked into the proposal.
The cost breakdown though is alarming. According to the Port Authority’s engineers, the building would come with nearly $6 billion in hard costs and nearly $3 billion in soft costs — planning, engineering, legal, professional, financing and insurance. To me, that sounds like the costs of corruption in the construction industry in New York City and not really the actual cost of building something new. The $10.5 billion price tag also includes $1.9 billion in contingencies.
Streetsblog had more from the meeting on costs:
[Skanska’s Mark] Gladden compared the bus terminal replacement to the UPS Worldport in Louisville, Kentucky, which handles virtually all of the shipping company’s domestic air freight. Built 15 years ago, he said, it cost $850 million. Taking inflation and construction cost increases into account, the project would likely cost $1.7 billion today. Moving the project to New York, with its higher construction costs, would double the price tag to $3.4 billion. The UPS project didn’t have the steel requirements and logistical challenges posed by operating a bus terminal in Midtown Manhattan, Gladden said, which contribute to the additional costs.
Gladden added that East Side Access and the Second Avenue Subway, multi-billion dollar projects under the management of many of the same consultants working on the Port Authority Bus Terminal, serve fewer people than the bus terminal. The bus terminal, built for 150,000 daily passengers, now handles 232,000, about as many as Grand Central Terminal. That number will reach as high as 337,000 by 2040.
“We recognize that projects of this magnitude and this complexity right at the very beginning result in sticker shock,” Gladden said. “We have a high level of confidence that this estimate, at this point in the program development, reflects an accurate or reasonably accurate cost.”
Based on the Port Authority’s comments today, the agency — and thousands of bus commuters — are stuck between a rock and a hard place. Much like other New York City infrastructure, the PABT is literally collapsing. It’s not designed to handle the crowds, and it will outlive its useful and functional live soon. But the Port Authority will have to find $10 billion to fund a replacement building and soon. How they do that — without a Spanish architect — remains to be soon. Perhaps they should consult Spanish construction firms though; at least they know how to build on the cheap.