Home Second Avenue Subway On building subway lines during recessions

On building subway lines during recessions

by Benjamin Kabak

Earlier today, I appeared on a story on Marketplace about the Second Ave. Subway and subway construction in general during tough economic times. You can listen to the story via the player at right or you can find it online right here. Jeremy Hobson and I spoke at length about the economics behind the Second Ave. Subway and the ongoing construction on the East Side, and his story explores why this economic downturn hasn’t yet killed the Second Ave. Subway as the downturn in the 1970s did.

To summarize my thoughts briefly, the issue comes down to both the politics and mechanisms of the current funding. Much of the money for the project was secured before the economy went south, and the federal dollars are specifically earmarked for the Second Ave. Subway construction. In the 1950s, the transit agency could siphon funds away from the project to invest in other areas of maintenance while in the 1970s, the costs were funded through a scheme that resembled a pay-as-you-go structure. The Feds ensured that the money would be there this time around, and the MTA can continue to work through a bad economy.

Additionally, the Second Ave. Subway, while not a stimulus-funded project, acts as one anyway. By continuing work, the MTA continues to employ contractors and construction crews. Constant investment in this decade-long project creates constant jobs, and to kill it now would be politically ugly and economically unwise.

In the end, as I said to Hobson, I am uncertain of the future of Phases III and IV of the Second Ave. Subway. Phase II relies on preexisting tunnel, and Phase I, I believe, will finish. But beyond that, the money and the timeline remains ever so out of reach. For now, though, construction continues apace along Second Ave.

You may also like

9 comments

Rob November 23, 2009 - 12:24 pm

Well done!

Reply
Marc Shepherd November 23, 2009 - 12:45 pm

It is highly misleading to say that Phase II “relies on preexisting tunnel,” as if to suggest that this makes it cheaper or easier.

In the Final Environmental Impact Statement, the costs given for Phases I and II were $3.8 billion and $3.4 billion respectively. Obviously those costs are no longer accurate, but it gives an idea of the relative degree of difficulty of the two phases. The existence of a portion of the tunnel doesn’t make Phase II much cheaper.

Reply
Benjamin Kabak November 23, 2009 - 12:48 pm

No one has said that Phase II will be “much” cheaper, but as your numbers point out, the initial estimates had Phase II more than ten percent cheaper than Phase I. Even with rising costs, that’s not insignificant.

Additionally, because of the existence of the tunnels north of 96th St., there will be a good amount of pressure on the MTA to make use of those through Phase II. I maintain that we’ll see it happen, and there’s nothing “highly misleading” about that.

Reply
Marc Shepherd November 23, 2009 - 1:08 pm

When most people see your comment that Phase II relies on existing tunnel, and if they have not seen the FEIS, they conclude that it will be a lot cheaper to build. In that sense, I think you are misleading people.

The 10% cost difference is insignificant. It is normal for cost estimates to have at least a 10% error factor, so to a first-order approximation Phases I and II cost the same amount. You can therefore assume that the MTA will have as much trouble funding Phase II as it has had funding Phase I.

I say that as someone who wants all four phases to happen. But we need to understand that, realistically, the existence of an already-built tunnel for part of the route does not help very much.

Reply
Nathanael December 24, 2009 - 11:56 pm

Some of the confusion arises from the fact that Phase II could easily be split into a Phase IIA (to 106th and 116th Streets) and a Phase IIB (to 125th St.)

Phase IIA relies mostly on existing tunnels, consists essentially of building two stations, and will be *much* cheaper than Phase I.

Phase IIB involves entirely new tunnels, which must be curved and sloped (so, mined by hand largely), must feature bellmouths for a turnout to a future line to the Bronx, and terminate in a station underneath both the IRT tunnels and Metro-North viaduct — requiring extensive and complex underpinning. It’s not East Side Access, but it’s much more complex than Phase I.

Reply
Ed November 23, 2009 - 1:24 pm

Benjamin – appreciate the post, but word in NYC political circles has it that Phase I is in real jeopardy right now, there are large and growing budget gaps even for this first phase – sucks but not hard to see.

The Launch Box recently mentioned this gap – $1.5B at least that is NOT funded:

“Page 2 of the report shows a budgeted amount of $1.487 Billion for the “Second Avenue Subway that has not yet been funded. This amount is part of the MTA’s proposed 2010-2014 Capital Program, and all of this amount is scheduled to be provided by “local sources,” which I assume means New York State.

As reported on 2nd Ave. Sagas in early October, Governor Paterson has called the MTA’s 2010-2014 Capital Program “simply unaffordable given New York’s current fiscal condition.” One has to wonder if there is any chance that construction could be held up, or even stopped, because of the current fiscal crisis – which would be just like what happened to the project back in the 1970s.”

http://thelaunchbox.blogspot.c.....-2009.html

Reply
Benjamin Kabak November 23, 2009 - 2:30 pm

Ed: I hope you appreciate the amusing aspect of what you just did. You told me that Phase I is in “real jeopardy” by citing a Launch Box blog post that cited one of my posts from October. I’m well aware that not all of the SAS has funding yet, and I’m well aware that Paterson is hedging on fully funding the MTA’s capital plan. But the agency has the funding for two-thirds of the plan, and you can bet that this $20 billion will cover the rest of the Phase I budget.

Reply
Julia November 23, 2009 - 10:26 pm

Congrats on the press coverage!

Reply
Woody November 23, 2009 - 10:28 pm

According to the Center for Arms Control and Non-Proliferation, we’re spending $265 million a day in Afghanistan and about $400 million a day in Iraq. If we could get out of Iraq and Afghanistan for just three (3) days, the savings from peace would cover the unfunded $1.5 billion portion of Phase I, with enough left over for the usual cost overruns.

Pardon my daydreaming.

Reply

Leave a Comment