
For the most part, the abandoned subway stations dotted through the city are remnants of subway service past. The 91st St. station located beneath by childhood apartment building flashes by in the blank of an eye, and the Bergen St. express stop — destroyed in a fire — is visible only during the right GOs. Then, there are the stations never used such as the mythical South 4th St. stop or the lower level at Nevins Street. Urban explorers and city historians know about these secrets.
But what of the station that’s pre-abandoned? It one day will be used, but for now, it sits mostly finished but with no passengers. It’s the newest subway station in New York City, and it’s not yet set to open until, well, soon — perhaps by mid-summer if all eventually goes according to plan. I am of course referring to the 7 line extension at 11th Ave. and 34th St. As recent photos released by the MTA show, it’s a gleaming, bright, brand-new subway stop entirely devoid of people, and as a recent report released by the MTA shows, the station is likely delayed again until the start of the third quarter of 2015.
The latest new came out of Monday’s MTA Board committee hearings. As the Capital Construction committee books reveal, the MTA is “aggressively pursuing completion” before the end of June, but foundation work at a site underneath planned development and testing is likely to push that date into July. During Monday’s meeting, MTA officials confirmed that the June opening is unlikely, and a summer opening is in the 7 line extension’s future. Considering how unfinished the station looked in December of 2013 when Mayor Bloomberg had his ceremonial non-opening, we never should have believed the station would be ready in 2014 in the first place.
The source of the latest delays is two-fold. First, the MTA’s own testing issues are an impediment. The fire alarm and transmission-backbone systems are behind schedule while Transit is finally beginning Level 4 acceptance testing for those pesky incline elevators. The MTA and its consultants anticipates 15 weeks for remaining testing with two weeks’ lead time; hence, the July revenue service date.
Meanwhile, additional work at Hudson Yards — something that wouldn’t have been a problem a year ago — has reared its head. Site J was due to host a ventilation plant that wasn’t required for revenue service. Work was due to start around now, and, well, here comes the work. As crews seek to sink parts of the foundation near passenger areas, the MTA may need to coordinate schedules around this work. You may think this should have been a consideration earlier in the project, but here we are.

What is completely surreal about this project right now is that it’s a nearly finished subway station underneath the streets of Manhattan. You can skim through the photos in this PDF or take a stroll near the Javits Center. It’s not a particularly important stop for a few more months, and I’d wager that most New Yorkers have no idea it’s on the eternal verge of opening. But it’s there, awaiting completion for the past 15 months.
And yet, while it doesn’t really matter in the short-term if this station opens in June or July or last April or next September, it matters for the credibility’s sake. The MTA is asking for $15 billion for another capital fund, but it can’t open a one-station extension that was supposed to ready for service before 2013 ended. The cognitive dissonance is overwhelming. Meanwhile, according to MTA documents, Phase 1 of the Second Ave. Subway is still set to open by the end of December 2016. I think I’ll take the over.
Leave a Reply