When last we checked in on the Second Ave. Subway, the MTA Board had just heard a presentation regarding delays that may cause the project to miss its projected December opening date. Last month, the agency’s Independent Engineering Consultant warned of a “moderate risk of delay” should key activities remain outstanding and behind schedule. Yesterday, after a gap of only six weeks, the IEC returned with more warnings for potential delays, but the MTA reiterated its plan to have the Second Ave. Subway open before the year is out.
For its part, the MTA says it is ready to move testing and commissioning staff into on-site locations as soon as possible and is working with contractors to address and resolve any items that could delay the revenue service start date. The MTA also plans to implement “lessons learned” from the delayed openings of both the Fulton Street. Transit Center and the 7 line extension, but the IEC is skeptical these efforts will be sufficient. Noting new and backlogged change orders, the IEC said that it “has observed that several key activities slipped their scheduled completion dates in the six weeks since the December 2015 CPOC report. In particular, delays to provision of permanent power at 86th St and 96th Streets are of most concern as they could potentially impact the start of testing and commissioning.”
The IEC has recommended the MTA institute weekly meetings with its contractors “to properly status key activities and identify critical delays for mitigation and recovery” and has urged the agency to “complete the new integrated project schedule by integrating the communications testing with the accelerated testing of station equipment installations.” In other words, speed up the project schedule or else testing requirements won’t permit the MTA to open the northern extension of the Q train to 2nd Ave. and 96th St. by the end of December. The next IEC update is due in March.
In other news tangentially related to the Second Ave. Subway, Disney announced last week that Star Wars VIII will arrive in theaters in December of 2017 rather than in May. Last month, the overwhelming majority of those who voted in my poll felt that Star Wars would open before the Second Ave. Subway, but that was when the movie was scheduled for a summer 2017 release. I wonder if those results would hold in light of the new release date and the IEC warnings. My guess is that the Second Ave. Subway will miss the December 2016 date but open by the spring of 2017. Either way, the MTA has a lot riding on the next 11 months, and Upper East Side residents are watching closely.
Leave a Reply