In January of 2010, MTA Capital Construction announced an incremental benefit of East Side Access construction. Although at the time the project was not set to open until 2016, the MTA planned to debut a new entrance this September on 47th Street between Park and Lexington Avenues. It is not yet meant to be.
Many frequent Metro-North commuters had noted that the entrance hadn’t opened in September as planned, and I recently reached out to the MTA for an official statement on the delay. While the completion date for East Side Access has been delayed with a report on a new estimated date due out later this year, the entrance could have opened as planned. It was not meant to be, and now the MTA expects to ready this entry point early next year.
“We expect the entrance will open in the first quarter of 2012,” MTA spokesman Aaron Donovan said. “Metro-North has shifted to a more sophisticated security system for Grand Central, and the entrance needs to be made compatible with the new system.”
The new entrance, when it opens, will feature an escalator from the street to the 47th St. cross passageway and a staircase from the street to the platform shared by Tracks 11 and 13. Meanwhile, we’re stilling waiting for the bad news from MTA Capital Construction President Michael Horodniceanu concerning the estimated revenue service date for ESA. My money is on 2018.