In its original incarnation, the East Side Access project was to be completed by the second quarter of 2012. As we well know, that timeline has been pushed back by over four years to September 2016, but according to an MTA report, the agency is concerned that they may need to further delay the projected substantial completion date for the Long Island Rail Road connection into Grand Central.
In a document presented last week at the MTA Board committee meetings, MTA Capital Construction officials said “our confidence level in meeting the September 2016 revenue service date is low without significant mitigation.” Because of “on-going contractor delays in Manhattan and Queens” as well as some back-and-forth with Amtrak over the Harold Interlocking work, the MTA has nearly exhausted its schedule contingency, and thus, without mitigation work, the project is in danger of missing the September 2016 date.
According to the brief report, available here as a PPT document, Capital Construction is going to work with the LIRR to reassess construction sequencing and timing for the final sections. The Capital Program Oversight Committee will hear the suggestions and potential cost impacts in September.
Leave a Reply