The current contract plan for the Second Ave. Subway. (Via the MTA’s Sept. 24 presentation to CB 8. Click to enlarge.)
Over the weekend, a few SAS commenters got into a long discussion about the pace of work — or lack thereof — along Second Ave. People who are in the neighborhood on a daily basis see little day-to-day progress while those who come through the Upper East Side see that something has happened but aren’t quite sure what.
Meanwhile, as time ticks on, the MTA’s plans for a tunnel boring machine launch fall further behind schedule. At one point, the TBM work was set to wrap up by Christmas of 2009. Later on, the TBM should have launched in July. Now, with unstable buildings and negligent landlords plaguing construction, utility relocation work is progressing south of the launch box area, but the tunnel boring machine and the excavations that require blasting are in limbo.
A few weeks ago, at a Community Board 8 meeting, the MTA unveiled a new schedule of contracts for the Second Ave. Subway. Ben at The Launch Box wrote upsome observations and analysis of this new document, and I’ve posted it above. Click the thumbnail at right for a comparison to a schedule released three years ago on July 11, 2006.
If we didn’t know about the myriad delays that have plagued the Second Ave. Subway, it would be shocking to see a timeline of this project pushed back four years over the span of 36 months. With contract lengths receding ever on into the future, it is of little wonder that people in the neighborhood think nothing is getting done.
Off the bat, we can see that the TBM launch box duration is a major source of delay. Originally slated to take 37 months, that aspect of the project is now scheduled for 51 months. It didn’t get started on time and won’t wrap up until June 2011. The station work too is set for a longer timeline. In 2006, the MTA budgeted 54 months for the 96th St. station work, 25 months for a retrofitting of the current 63rd St. stop on the F and 49 months each for the stations planned for 72nd St. and 86th St. The systems work and test runs were to take 53 months.
Those timelines have been blown out of the water. The 96th St. station is set to take 72 months to build; the 63rd St. stop will be under construction for 30 months; the actual work on the 86th St. stop will take 60 months; and the 72nd St. stop will be completed in 62 months. Systems work will last for 67 months, and Transit plans to run non-revenue tests for three months before an estimated December 2016 completion date. At the Launch Box, Ben notes that overall construction time has increased from seven years and one month to nine years eight months.
So what then are the causes? Soon, the MTA Inspector General will release a report that promises to be critical of the pace of construction. The Launch Box targets four specific problem areas: Utility relocation took far longer than expected; contracts were awarded later than expected; final design elements were not finalized until late in the process due to requests from the community for additional review; and real estate acquisition and stabilization problems have slowed down the overall process.
In the end, we knew the Second Ave. Subway has suffered through delays. With the hard evidence, though, it’s very tough to believe the delays are a thing of the past and that this subway line will open by the end of 2016 or the start of 2017. At what point does the MTA throw in the towel? When do we look for surface-based, light-rail solutions to the East Side transit congestion problems? Can the city afford to wait another seven or eight years for a subway line that may never fully open when more cost-efficient solutions are out there?

Leave a Reply